Construction of Reservoir, Sedimentation Tank & Irrigation System at Berry Farms in Uzbekistan

1.

Construction of Reservoir,
Sedimentation Tank & Irrigation
System at Berry Farms in
Uzbekistan
Bi-weekly Report
20th February 2023

2.

Agenda
#
Description
1
Present the progress made during the past week (6th February to 20h of February).
2
Issues and concerns
2

3.

3
Dashboard
Project
Description:
Summary:-
2 sumps are being worked on in parallel and works are being carried
out in accordance with quality and standard rules
About 17 techniques are involved for water reservoirs till today
Earthwork excavations, leveling and compaction works are being
monitored daily
Reservoir: Excavation works commenced on 09.02.2023
Pre-water: Setting out completed.
Irrigation:
Project Performance:- Irrigation
System
Project Performance:Reservoir
700 000,00
649K
600 000,00
2 000 000,00
1 800 000,00
PV
1.749M
PV
1 600 000,00
Название оси
500 000,00
1 400 000,00
1 200 000,00
400 000,00
1 000 000,00
300 000,00
800 000,00
200 000,00
600 000,00
EV
EV
400 000,00
100 000,00
200 000,00
0,00
Название оси
SPI (value) = 1.24 = (EV/PV)
16/5
0,00
16/5
SPI (value) = 1.04
Legend:
Base Line –
Actual -
3

4.

5.

6.

Daily report of the number of machines
09.02.2023
10.02.2023
15.02.2023
16.02.2023
11.02.2023
21.02.2023
12.02.2023
13.02.2023
14.02.2023

7.

7
Reservoir & Pre-Waterpool
Progress
Overview:
Roads were made for the smooth movement
of machinery
Excavation in the segmentation tank is almost
complete
Photos:-
Reservoir:Development Key
Items
Agreed
Planned %
Actual
Var
Earthwork Excavation
10%
20%
10%
Levelling & Compaction
10%
17%
7%
Installation of Geo-Textile
0%
0%
0%
Installation of Geo-Textile
0%
0%
0%
Concrete Platform (1.5m wide)
0%
0%
0%
Installation of Fence
0%
0%
0%
Feb
Mar
Apr
May
UPDATED 20.02.2023
ON 30.06.22
Pre-Waterpool:Development Key
Items
Agreed
Planned %
Actual
Var
Earthwork excavation
20%
80%
60%
Gravel Filling & Compaction
Polyethene Film
Instalaltion - (Min 1000
Guage)
Concrete Base Slab
Installation of Water Bar
(bentotine)
Walls & Concrete Platform
10%
40%
30%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Feb
Mar
Apr
May
7

8.

8
Irrigation System
Progress
Overview:
Basically, Now, tranches of strawberry sub
main lines are excavated
almost 2000 trenches were dug
Photos:-
Irrigation System:-
2023
Development Key
Items
Status Update
Agreed
Planned
%
Actual
Var
Cherry Farm - Head Unit
100%
1%
99%
Cherry Farm - Main Line
0%
0%
0%
Cherry Farm - SubMain Line
0%
0%
0%
Irrigation Valves & RTU
0%
0%
0%
Drip Line and accessories
0%
0%
0%
Head Unit
0%
0%
0%
Main Line
100%
25%
75%
SubMain Line
100%
35%
65%
Irrigation Valves & RTU
0%
0%
0%
Drip Line and accessories
0%
0%
0%
Testing & Commissioning
0%
0%
0%
Feb
Mar
Apr
May
Blueberry , Blackberry, Raspberry & Strawberrry Farm
Handover
8

9.

Progress
Overview:Excavation works were started earlier on the Cherry line than
other crops and reached 120 meters and remained unchanged
until February 15.The strawberry line had a big increase within
3 days and rapidly reached 1152 meters from 100 meters till 13
February and nowadays this line is one of our leading lines. The
Raspberry Line was one of the weakest line until February 13.
However, in this day, it improved and reached 390 meters, and
3/1 of yesterday's work was done next day, Talking about one
of our lowest lines. It was the Blackberry line. On February 15th,
some effective digging was done and it went one step above
the lowest (186 m).
Fri
Sat
Sun
Mon
Tue
Overall length -25547 m = 100% (Total meter of excavation works)
Done -2162 m = 8,5 % (Total meter of completed work from 10 till 15 Feb)
Wed

10.

Photos on progress
Excavation works of Main and Submain lines
Excavation
works
(meter)
2000
1500
1000
500
0
10.02.2023
11.02.2023
12.02.2023
Submain Line
13.02.2023
Main Line
14.02.2023
15.02.2023

11.

Irrigation System
1th instalment on contract
Description
Done
Left
-Engineering and Design
100%
0%
-Trench Excavation & Back
10%
90%
-Transportation
50%
50%
34%
66%
Maximum completion
time of the works
Feb 6
1th instalment
$0,00
10
15
20
Feb 28
34%
$14,00
$28,00
10
15
20
Mar 31
66%
$42,00
$56,00
Actual
Planned
$70,00
$84,00
$98,00 $112,00

12.

Sediment Basin and Water Reservoir
1th instalment on contract
Description
Done
Left
-Water pool Earthwork excavation,
ramming and removal
30%
70%
-Sediment basin Earthwork
excavation, ramming and removal
80%
20%
31%
69%
Maximum completion
time of the works
Feb 6
1th instalment
$0,00
Feb 28
31%
$25,00
Mar 20
69%
$50,00
$75,00
Actual
$100,00
Planned
$125,00
$150,00
$175,00
$200,00

13.

Area of Concerns
ISSUES & CONCERNS
• Due to the fact that it is winter now, there are problems with moving equipment in the field, earthwork excavation of segmentation
and main tanks, compaction them, and digging trenches. Techniques are sinking in the mud.
• A separate working group has been assigned the task of completing the amenities specified on Appendix A.
• Due to the fact that there are residential areas around the facility, the technics cannot work until late at night
13

14.

Project Schedule (Reservoir)
Legend:
Base Line –
Actual -
14

15.

Project Schedule (Irrigation)
Legend:
Base Line –
Actual -
15

16.

Project Schedule (Irrigation)

17.

Progress Photos
1717

18.

Progress Photos
1818

19.

On Appendix A

20.

21.

22.

23.

24.

25.

Debuyt
P.O. Box 2297, Abu Dhabi,
United Arab Emirates
[email protected]
+971 2 554 1000
agritek.ae
Thank You