LECTURE 38–39Pile Works and
Pile Installation
Methods
Equipment, process control and method
selection
Prepared by: S. Niyetbay
01
2.
CHAPTER 38Why pile foundations are used
Piles transfer loads to deeper soil, improve weak ground
performance and control settlement.
• They bypass weak near-surface layers and mobilize end bearing, shaft resistance or
both.
• They support industrial buildings, tanks, retaining structures and deep underground
facilities.
• The construction method must match the soil profile, groundwater, pile material and
site restrictions.
70–75%
25–30%
1.5–2×
possible reduction in
earthworks
possible concrete saving
lower labour for underground work
02
3.
PILE CONSTRUCTION TECHNOLOGYPile classification and installation routes
Driven piles
Cast-in-place piles
• Manufactured before installation
• Installed by impact, vibration, pressing or
screwing
• Immediate structural element after
installation checks
• Formed inside the ground
• Require boring or excavation and
concreting
• Useful where large sections or deep
underground structures are required
These chapters focus on the installation of prefabricated piles.
03
4.
PILE CONSTRUCTION TECHNOLOGYSite preparation before pile installation
• Set out the pile field after grading the working
platform.
• Mark pile rows with perpendicular control lines and
stable reference points.
• Arrange storage so the rig can lift piles with minimal
travel.
• Provide power, water, lighting and safe crane access.
• Perform trial driving before full production and update
the work plan if required.
Set-out control points should
project about 10–12 cm above the
surface.
04
5.
CHAPTER 39Core installation cycle
4
Measure penetration and
resistance
2
Lift and align the pile
5
Complete dynamic or static
testing
3
Install to the required depth
6
Record the final level and
acceptance data
1
Move and position the rig
The sequence remains similar across methods. Equipment and control
parameters change.
05
6.
PILE CONSTRUCTION TECHNOLOGYImpact driving equipment
• The leader guides both the pile and hammer.
• Self-propelled rigs commonly handle piles 6–
10 m long.
• Rigs based on cranes, tractors, trucks or
excavators improve mobility.
• Universal tower rigs suit piles longer than 12
m but need rail tracks and greater setup effort.
Equipment selection must include the
mass of the pile, hammer and lifting
system.
06
7.
PILE CONSTRUCTION TECHNOLOGYPile handling and leader alignment
• Move the pile from storage with controlled
lifting points.
• Connect the pile head to the hoisting line and
guide it into the leader.
• Align the pile in plan and vertically before the
first blow.
• Use special pull-up devices for 6–8 m piles
where required.
• Poor alignment creates bending, head damage
and positional error.
07
8.
PILE CONSTRUCTION TECHNOLOGYHammer types and operating rates
• Single-acting steam-air hammers: typically 10–15
blows per minute.
• Double-acting hammers: more than 200 blows per
minute.
• Rod diesel hammers: about 50–60 blows per minute.
• Tubular diesel hammers: about 47–55 blows per
minute.
• Tubular diesel hammers provide greater impact
energy for the same striker mass.
10–15
>200
blows/min, single-acting
blows/min, double-acting
08
9.
PILE CONSTRUCTION TECHNOLOGYHammer mass and impact energy
The hammer must deliver enough energy without overstressing the
pile.
• For a 12 m pile in dense soil, a free-fall striker may be about 1.5 times the mass of the
pile and helmet.
• In medium-density soil, the ratio may reduce to about 1.25.
• The adopted applicability coefficient depends on pile material and hammer type.
• Use a pile helmet and cushioning system to distribute the blow and protect the pile
head.
1.5×
1.25×
dense soil: striker to pile + helmet mass
medium-density soil ratio
09
10.
PILE CONSTRUCTION TECHNOLOGYImpact driving procedure and control
• Start with a low hammer drop, usually no more than 0.4–
0.5 m, to establish alignment.
• Count blows per metre during initial penetration.
• Near the final depth, record penetration for each control
set.
• Single-acting and suspended hammers commonly use 10
blows per set.
• Double-acting and diesel hammers use one minute of
operation as the control set.
0.4–0.5 m
maximum initial drop height
10 blows
typical control set
1 mm
maximum set measurement error
10
11.
PILE CONSTRUCTION TECHNOLOGYRefusal, redriving and acceptance
Refusal is the measured penetration per blow or per control set near
the end of driving.
• Compare the measured final set with the design value.
• If refusal is not achieved, stop and investigate instead of continuing uncontrolled driving.
• Piles may be redriven after a soil-rest period of about 3–4 days.
• If penetration reaches less than 85% of the design depth and three consecutive sets meet the
calculated refusal, review the cause with the designer.
• Dynamic testing estimates bearing capacity from driving resistance and hammer energy.
3–4 days
85%
typical soil-rest period before redriving
depth threshold requiring review
11
12.
PILE CONSTRUCTION TECHNOLOGYVibratory and vibro-impact methods
• Vibration reduces shaft friction and toe
resistance during penetration.
• Low-frequency vibrators suit heavy
reinforced-concrete piles and tubular piles.
• High-frequency units suit light piles and
sheet piles with low toe resistance.
• The method performs best in loose, watersaturated, non-cohesive soils.
• Vibro-impact equipment combines oscillation
with repeated impact.
≤420/min
≥1500/min
low-frequency vibration
high-frequency vibration
12
13.
PILE CONSTRUCTION TECHNOLOGYVibration design checks
• The combined oscillating mass must overcome soil resistance and maintain stable vertical motion.
• For light reinforced-concrete piles, the eccentric moment should exceed the oscillating mass by at
least 7 times in light soils and 11 times in medium or heavy soils.
• For reinforced-concrete piles, the vibro-impact striker should be at least 50% of the pile mass.
• A typical striker mass range is 650–1350 kg.
• In cohesive soil, finish the last 15–20 cm by impact to remove the weakened soil cushion under
the toe.
≥50%
650–1350 kg
striker mass relative to RC pile mass
typical vibro-impact striker mass
13
14.
PILE CONSTRUCTION TECHNOLOGYStatic pressing and vibropressing
• Static pressing uses reaction mass to push the
pile without impact.
• A typical installation can develop about 350 kN
of pressing force.
• It may install 13–15 piles per shift when pile
length is up to 6 m.
• Vibropressing combines static force with a
suspended low-frequency vibrator.
• The method reduces pile damage and works
well where vibration and noise limits are
important.
350 kN
13–15
typical pressing force
piles per shift, up to 6 m
14
15.
PILE CONSTRUCTION TECHNOLOGYScrew pile installation
• A rotary drive turns a steel or reinforcedconcrete pile with a helical toe.
• The rig can install piles vertically or at an
inclination.
• The installation angle may vary from 0° to 45°
from vertical.
• The same equipment can reverse rotation for
pile extraction.
• Screw piles are effective for transmission-line
and tower foundations where uplift resistance
matters.
0–45°
installation inclination from vertical
15
16.
PILE CONSTRUCTION TECHNOLOGYWater-jet-assisted installation
• Water jets loosen soil around the pile and reduce toe
resistance.
• Typical jet-pipe diameter: 38–62 mm.
• Place side nozzles 30–40 cm above the toe and the
encircling nozzle 150–200 cm above it.
• Water pressure should be at least 0.5 MPa.
• Stop jetting when the toe is about 0.5 m above design
level, then finish without jetting.
• Do not use this method in collapsible soils or near
structures sensitive to settlement.
≥0.5 MPa
0.5 m
minimum water pressure
finish without jetting
16
17.
PILE CONSTRUCTION TECHNOLOGYElectro-osmosis assistance
A direct electric field changes water movement around steel piles in
clayey soil.
• Connect the pile being installed as the cathode. Soil moisture increases around it and
resistance decreases.
• Use a previously installed pile as the anode. Soil moisture decreases around the anode.
• After switching off the current, groundwater conditions gradually recover.
• Temporary electrodes can cover about 20–50% of the pile surface.
• The method is used mainly for steel piles and is commonly combined with screw
installation.
The method changes soil-water conditions. Electrical safety and nearby buried services
require special control.
17
18.
PILE CONSTRUCTION TECHNOLOGYPile installation in frozen ground
• Direct impact or vibration may remain practical
when seasonal frost depth is no more than about 0.7
m.
• For deeper frost, thaw the soil, predrill holes or cut
slots along the pile rows.
• Steam thawing may use pressure of about 0.4–0.8
MPa.
• Predrilled holes should be about 2–3 times the
maximum pile cross-section.
• For reliable test results, allow the pile-soil system
to refreeze before control testing.
≤0.7 m
direct installation through seasonal
frost
18
19.
PILE CONSTRUCTION TECHNOLOGYFrozen-ground effects on capacity
Freezing can lock the pile to the surrounding ground and distort early
test results.
• When frozen soil is disturbed around a driven cylindrical pile, bearing capacity may initially
decrease by 15–20%.
• After thawing, capacity may increase by about 10–15%.
• Steam needles can thaw small-ice-content soil in about 1–3 hours.
• Highly ice-saturated ground may require about 6–8 hours.
• The borehole diameter should be about 2–3 times the pile section to permit installation.
−15–20%
+10–15%
possible initial capacity reduction
possible increase after thawing
19
20.
PILE CONSTRUCTION TECHNOLOGYPile-driving sequence
• Use row-by-row driving for regular grids and pile
groups.
• Use a spiral pattern from the perimeter toward
the centre when it reduces rig travel and soil
displacement problems.
• If pile spacing is less than about five pile
diameters, soil inside the group can densify and
make later piles difficult to install.
• Coordinate pile driving with caps, beams and
access routes.
• The sequence must remain explicit in the work
method statement.
<5D
spacing that can intensify group effects
20
21.
PILE CONSTRUCTION TECHNOLOGYPile extraction and temporary works
• Extract temporary sheet piles with hydraulic devices, winches, double-acting hammers or
vibratory extractors.
• Start where soil resistance is expected to be lowest.
• After the first pile or sheet-pile pair, the remaining elements usually require less pulling
force.
• Typical extraction speed: about 3 m/min in sand and 1 m/min in clay.
• Cut timber piles mechanically when extraction is unnecessary. Cut steel sheet piles with
suitable thermal cutting equipment.
3 m/min
1 m/min
typical extraction rate in sand
typical extraction rate in clay
21
22.
PILE CONSTRUCTION TECHNOLOGYEquipment productivity and fleet size
Observed productivity for 7 m reinforced-concrete piles with a 300 ×
300 mm section: 16–23 piles per shift.
Shift productivity
Fleet size
P = Kᵤ × 492 / (t₀ + tₐ)
N = S / (P × T)
• Kᵤ: time-utilization factor, often taken as 0.9
• t₀: main pile-installation time
• tₐ: auxiliary time and rig movement
• S: total number of piles
• T: available shifts
22
23.
PILE CONSTRUCTION TECHNOLOGYMethod-selection matrix
Impact
Vibration
Pressing
Screwing
Broad soil range,
strong monitoring of
noise and vibration
Best in loose
saturated noncohesive soils
Low impact on the
pile and surrounding
structures
Useful for uplift
resistance and
reversible installation
Selection factors: soil profile, groundwater, pile type, depth, required
production rate, nearby structures, noise, vibration and access.
23
24.
PILE CONSTRUCTION TECHNOLOGYField-control checklist
• Confirm the pile, rig, hammer and helmet match the approved method.
• Verify set-out, verticality or design inclination before installation.
• Record blow count, penetration rate, energy or pressing force as required.
• Protect the pile head and inspect for cracking, spalling or buckling.
• Stop and investigate abnormal refusal, sudden penetration or loss of alignment.
• Complete acceptance testing and as-built records.
• Maintain safe exclusion zones around suspended piles and operating equipment.
Reliable pile construction depends on controlled installation data, not only the
final depth.
24
25.
KEY TAKEAWAYSPile installation is a controlled ground–structure
process
01
Choose the method from soil behaviour and pile type.
02
Match hammer energy or pressing force to the pile.
03
Control alignment, penetration rate and final refusal.
04
Adapt the process for water, frost and nearby structures.
05
Plan the driving sequence and equipment productivity.
25