Похожие презентации:
Reservoir simulation
1.
RESERVOIR SIMULATIONCourse Name: Fundamentals of Reservoir Simulation
Instructor: Dr. Ye Tian
Student Name: ABDUSHUKUR SOBIROV
ID: 201839010031
Grade 2018 PE
2.
SIMULATION ACCURACY DEFINITIONSimulation is a technique of modeling real-life activity that
closely matches real-world outcomes for training purposes
to solve real-world problems.
3.
Matrix representation for system of equation4.
Given that:Porosity
K, mD
delta X, m
Cpore, MPa-1
Cfluid, MPa-1
Oil Viscosity, cP
delta t, day
Density, g/cm3
0.3
0.5
5
1.00E-04
5.00E-04
5
10
0.76
5.
Solving 1D Phase Simulation• We have total 21 Nodes so our matrix will be a 21*21 matrix
6.
• We need to keep the pressure constant at 10 Mpa• Then we have to use the matrix equation to solve the pressure of Day 1.
7.
• Then create the graph for Day 10, 50 and 1008.
• The node at the left-end is open to a constant production rate of 0.1t/day
9.
• pressure distribution at day 10, day 50, and day 100.10.
• The node at the left-end is open to a constant production rate of 0.1t/day.
• The node at the right-end is open to a constant injection rate of 0.2
t/day.