Construction of Reservoir, Sedimentation Tank & Irrigation System at Berry Farms in Uzbekistan (27th March 2023)

1.

Construction of Reservoir,
Sedimentation Tank & Irrigation
System at Berry Farms in
Uzbekistan
Bi-weekly Report
27th March 2023

2.

Agenda
#
Description
1
Present the progress made during the past week (20th March to 27th of March).
2
Issues and concerns
2

3.

3
Dashboard
Project
Description:
Summary:-
2 sumps are being worked on in parallel and works are being carried
out in accordance with quality and standard rules
About 17 techniques are involved for water reservoirs till today
Earthwork excavations, leveling and compaction works are being
monitored daily
Reservoir: Excavation works commenced on 09.02.2023
Pre-water: Setting out completed.
Irrigation:
Project Performance:- Irrigation
System
Project Performance:Reservoir
700 000,00
649K
600 000,00
2 000 000,00
1 800 000,00
PV
1.749M
PV
1 600 000,00
Название оси
500 000,00
1 400 000,00
1 200 000,00
400 000,00
1 000 000,00
300 000,00
800 000,00
200 000,00
600 000,00
EV
EV
400 000,00
100 000,00
200 000,00
0,00
Название оси
SPI (value) = 1.24 = (EV/PV)
16/5
0,00
16/5
SPI (value) = 1.04
Legend:
Base Line –
Actual -
3

4.

4
Reservoir & Pre-Waterpool
Progress
Overview:
Every day, 2000 cubic meter of soil are being
excavated from main water
Excavation in the segmentation tank have
been already completed
Photos:-
Reservoir:Development Key Items
Agreed
Planned %
Actual
Var
Earthwork Excavation
90%
89%
-2%
Installation of Geo-Textile
0%
0%
0%
Installation of Geomembrane
0%
0%
0%
Concrete Platform (1.5m wide)
0%
0%
0%
Installation of Fence
0%
0%
0%
Feb
Mar
Apr
May
UPDATED 19.03.2023
ON 30.06.22
31.08.2022
#######
Pre-Waterpool
Development Key
Items
Agreed
Planned %
Actual
Var
Earthwork excavation
100%
100%
0%
Gravel Filling & Compaction
100%
100%
0%
Polyethene Film
Instalaltion - (Min 1000
Guage)
0%
0%
0%
Concrete Base Slab
0%
0%
0%
Installation of Water Bar
(bentotine)
0%
0%
0%
Walls & Concrete Platform
0%
0%
0%
Feb
Mar
Apr
May
4

5.

5
Reservoir & Pre-Waterpool (time to deliver the job)

Name of work (MAIN RESERVOIR)
Time to deliver the job
Actual
1
Earthwork excavation
8 February – 31 March (51 days)
88,5%
3
Installation Geo-Textile
25 March – 5 April (11 days)
0%
4
Installation Geo-Membrane
5 April – 25 April (20 days)
0%
5
Concrete platform (1.5 wide)
25 April – 15 May (20 days)
0%
6
Installation of Fence
15 May – 23 May (8 days)
0%

Name of work (SEDIMENTATION BASIN)
Time to deliver the job
Actual
1
Earthwork excavation
8 February – 10 March (30 days)
100%
2
Gravel Filling & Compaction
8 February – 10 March (30 days)
100%
3
Polythene Film Installation (1000 Min Gauge)
10 March – 15 March (5 days)
0%
4
Concrete Base Slab
31 March – 10 April (10 days)
0%
5
Installation Water Bar
25 March – 20 April (26 days)
0%
6
Walls & Concrete Platform
20 March – 31 March (11 days)
0%

6.

6
Irrigation System
Trench Excavation
Irrigation System:-
Basically, Now, tranches of strawberry sub
main lines are excavated
almost 2000 trenches were dug
Agreed
Planned
%
Actual
Var
Tranch excavation & Back
75%
69%
6%
Cherry Farm - Head Unit
0%
0%
0%
Cherry Farm - Main Trench Line
15%
10%
5%
Cherry Farm - SubMain Trench Line
95%
88%
7%
Irrigation Valves & RTU
0%
0%
0%
Drip Line and accessories
0%
0%
0%
Head Unit
0%
0%
0%
Main Trench Line
90%
89%
1%
SubMain Trench Line
80%
78%
2%
Irrigation Valves & RTU
0%
0%
0%
Drip Line and accessories
0%
0%
0%
Testing & Commissioning
0%
0%
0%
Feb
Mar
Development Key Items
Photos:-
Apr
May
Blueberry , Blackberry, Raspberry & Strawberrry Farm
Handover
6

7.

Irrigation System (Main and Submain Lines of Farm)
Trench
25 547 long meter of trench
Excavation
100%
6379 meter
Irrigation System:100%
100%
100%
12830 meter
1625 meter
4713 meter
88%
11290 meter
89%
1446 meter
78%
3676 meter
15%
956 meter
Main Line (cherry)
Submain Line (cherry)
Main Line (Blueberry)
Black berry
Raspberry
Strawberry
Submain Line (Blueberry)
Black berry
Raspberry
Strawberry
7

8.

8
Irrigation System (time to deliver the job)

Description of works
Time to deliver the job
Actual
1
Tranch excavation & back
10 February – 30 March (48 days)
69,16%

Cherry Farm
Time to deliver the job
Actual
1
Cherry Farm –Head Unit
31 March – 10 April (10 days)
0%
2
Cherry Farm –Main Trench Line
5 March – 30 March (25 days)
11,8%
3
Cherry Farm –Submain Trench Line
10 February – 30 March (48 days)
88,15%
4
Irrigation valves & RTU
5 April – 10 May (35 days)
0%
5
Drip Line and accessories
5 April – 25 May (20 days)
0%

Blueberry, Blackberry, Raspberry, strawberry
Time to deliver the job
Actual
1
Head Unit
31 March – 10 April (10 days)
2
Main Trench Line
11 February – 30 March (47 days)
88,61%
3
Submain Trench Line
13 February – 30 March (45 days)
78,35%
4
Irrigation valves & RTU
5 April – 10 May (35 days)
0%
5
Drip Line and accessories
5 April – 27 May (52 days)
0%
6
Testing & Commissioning
25 May – 27 May (2 days)
0%
7
Handover
27 May – 31 May (2 days)
0%

9.

9
Irrigation System –lying pipe
Pipe Lying
Irrigation System:-
Pipe Lying started
16,03,2023
2023
Photos:-
Status Update
Actual
Var
Development Key Items
Agreed
Planned
%
Total percentage of Pipe Lying
50%
38%
12%
Cherry Farm - Main Line (pipe)
0%
0%
0%
Cherry Farm - SubMain Line (pipe)
50%
38%
12%
Main Line (pipe)
0%
0%
0%
SubMain Line (pipie)
0%
0%
0%
Feb
Mar
Apr
May
Blueberry , Blackberry, Raspberry & Strawberrry Farm
9

10.

10
Irrigation System (time to deliver the job on pipe lying)

Description of works
Time to deliver the job
Actual
1
Total percentage of Pipe Lying
16 March – 18 April (33 days)
38,40%

Cherry Farm
Time to deliver the job
Actual
1
Cherry Farm –Main Line
25 March – 10 April (16 days)
0%
2
Cherry Farm –Sub Main Line
16 March – 5 April (20 days)
38,40%

Blueberry, Blackberry, Raspberry, strawberry
Time to deliver the job
Actual
2
Main Trench Line
06 April – 18 April (12 days)
0%
3
Submain Line
02 April – 14 April (12 days)
0%
25 547 long meter main and submain pipe

11.

Area of Concerns
ISSUES & CONCERNS
• Due to the fact that it is winter now, there are problems with moving equipment in the field, earthwork excavation of segmentation
and main tanks, compaction them, and digging trenches. Techniques are sinking in the mud.
• A separate working group has been assigned the task of completing the amenities specified on Appendix A.
• Due to the fact that there are residential areas around the facility, the technics cannot work until late at night
All information given in percentages are shown regarding 4 days (from 20st till 27th March)
Main Reservoir
• Earthwork excavation was done 14% for 7 days. Excavation works reached 88,5%.
Irrigation system
• Trench excavation & Back reached 69,16%.
• Total percentage of Pipe Lying was done 31,74% within 7 days and reached 38,40% from 100%
11

12.

Project Schedule (Reservoir)
Legend:
Base Line –
Actual -
12

13.

Project Schedule (Irrigation)
Legend:
Base Line –
Actual -
13

14.

Project Schedule (Irrigation)

15.

16.

17.

18.

19.

20.

Progress Photos
2020

21.

Progress Photos
2121

22.

Debyut
P.O. Box 2297, Abu Dhabi,
United Arab Emirates
[email protected]
+971 2 554 1000
agritek.ae
Thank You
English     Русский Правила