LECTURE 9Crane Selection and
Techno-Economic Evaluation
Erection works: from project data to a safe and economical
crane solution
CONSTRUCTION TECHNOLOGY
A crane is suitable only when
capacity, height, radius, boom
geometry and stability meet the
governing lift simultaneously.
Prepared by: Niyetbay S.E.
09
2.
Learning outcomes02
BY THE END OF THE LECTURE
01
Initial data
CORE RULE
Read the building, site and erection sequence as one system.
02
Work quantities
Prepare the work nomenclature and calculate installation volumes.
03
Crane parameters
Determine capacity, hook height, radius, boom length and load moment.
04
Crane type
Select a mobile jib crane or tower crane using actual load charts.
05
Economic choice
Compare safe alternatives by cost, duration, productivity and labour
input.
One governing lift
must satisfy every parameter at the
same time
Qreq
capacity
Hreq
hook height
lreq
radius
Lreq
boom length
Mreq
load moment
3.
From project data to work quantities1
Project and site data
2
Erection sequence
03
3
Quantity takeoff
Structural layout
Installation order
Work item
Element dimensions and
masses
Temporary stability
Unit of measurement
Topography and ground
conditions
Rigging method
Quantity
Access and storage zones
Crane movement or track
layout
Design note
The governing case may be the heaviest, highest or farthest element. Check all three.
4.
Required crane parameters04
REQUIRED
CAPACITY
HOOK HEIGHT
HOOK RADIUS
BOOM LENGTH
LOAD MOMENT
Qreq
Hreq
lreq
Lreq
Mreq
tonnes
metres
metres
metres
t·m
WHAT EACH PARAMETER CONTROLS
Qreq
element + rigging at the actual radius
Hreq
vertical clearance for lifting and positioning
lreq
horizontal distance from rotation axis to load
Lreq
geometry required to reach height and radius
Mreq
combined effect of load and radius
Manufacturer capacity must be checked at the actual working radius.
5.
Mobile jib crane: geometric selection05
HOW TO READ THE DIAGRAM
1
The crane stands outside the building
and lifts over the erected structure.
2
Points O′ and O″ show the closest
critical positions to the boom.
3
4
Figure 1. Geometric parameters for a mobile jib crane
Hook height combines structure,
element, rigging and manoeuvring
height.
Boom geometry must clear both the
load and the building.
Clearance to element ≥ 0.5 m
Clearance to building: 0.5–1.5 m
6.
Mobile craneMobile
cranecalculations
calculations
06
REQUIRED HOOK RADIUS
lreq = ((a + d′)(Hreq − hsh))/(hp + hc) + c
lreq = ((b + d″)(Hreq − hsh))/(hp + hc + he +
h3) + c
BOOM GEOMETRY
Lreq = √((lreq + c)² + (Hreq − hsh)²)
loper = c + Loper cos αoper
Final checks
1
Ground or temporary platform resists outrigger or
track reactions.
2
Available capacity at loper is not less than Qreq.
3
Hook height and boom length meet the calculated
geometry.
4
Counterweight swing, access and overhead
hazards remain clear.
5
Wind limits, rigging capacity and communication
procedures are defined.
Reducing radius can sharply increase available
capacity and stability.
7.
Tower crane: geometric selection07
DECISIVE PARAMETERS
HOOK HEIGHT
Hreq
from crane standing level
FARTHEST RADIUS
lreq
to centre of gravity
Manoeuvring allowance
Figure 2. Geometric parameters for a tower crane
h3 = 0.5–1.0 m
8.
Tower cranecrane calculations
Tower
calculations
08
REQUIRED HOOK HEIGHT
Hreq = h0 + h3 + he + hc
Support level + manoeuvring clearance + element height + rigging height
REQUIRED RADIUS
LOAD CHART CHECK
The farthest element
may govern even when
it is not the heaviest.
lreq = a/2 + b + c
Half track gauge + distance to building + distance to farthest element centre
GOVERNING LOAD MOMENT
Mi = Pi li Mreq = max(Mi)
Check every representative element at its installation radius
Capacity depends on radius,
jib configuration, support
condition and operating
zone.
Use the manufacturer chart for
the selected configuration.
9.
Technical comparison of crane types09
Criterion
Mobile jib crane
Tower crane
Best application
Shorter projects and separated work zones
Repeated lifts over a large plan
Mobilization
Faster, but may require repeated setup
Longer installation and dismantling
Working radius
Capacity can decrease sharply with radius
Continuous coverage; capacity falls toward jib tip
Site demand
Stable platforms and access routes
Dedicated track or foundation
Main advantage
Mobility and flexible positioning
High erection rhythm
Main limitation
Frequent repositioning and outrigger restrictions
High initial setup cost and fixed position
Technical suitability comes before economic comparison.
10.
Techno-economic comparisonTechno-economic
comparison
10
REDUCED COST
DECISION RULE
Zγ = Cγ + En Σ(Φi Toi / mzi)
Direct project cost + annualized equipment capital cost
COST COMPONENTS
Mobilization
delivery, assembly, testing and dismantling
Site works
tracks, foundations, platforms or outrigger pads
Operation
energy, fuel, maintenance and operator
Labour
rigging, signalling and temporary fixing
Schedule
relocation, weather and interference downtime
Choose the
minimum reduced
cost
among alternatives that
already meet every technical
and safety requirement.
A lower hourly rental rate does
not guarantee the lowest total
project cost.
Compare the complete system of machines and workers.
11.
Crane quantity and labour inputP
Kaux
11
REQUIRED NUMBER OF CRANES
TOTAL LABOUR INPUT
Ncr = P Kaux / (Tm Πs A)
Tlab = Eonce + Σ(Mi ti) + Tmanual
total erection volume
Eonce
delivery, assembly and dismantling
labour
Mi ti
labour related to machine operating
hours
Tmanual
manual work outside machine-hour
norms
auxiliary-work coefficient
Tm
required duration in shifts
Πs
one-crane productivity per shift
A
working shifts per day
Typical Kaux ≈ 1.05–1.20
Productivity affects both crane count and the total project duration.
12.
Short calculation example12
INPUT DATA
Element
Rigging height
6.8 t
2.2 m
Rigging
Track gauge
0.7 t
6.0 m
Support level
Track to building
18.0 m
2.0 m
Clearance
Farthest centre
0.8 m
18.0 m
Element height
3.0 m
CALCULATION
7.5 t
1
Qreq = 6.8 + 0.7
2
Hreq = 18.0 + 0.8 + 3.0 + 2.2
24.0 m
3
lreq = 6.0/2 + 2.0 + 18.0
23.0 m
4
Mreq = 7.5 × 23.0
172.5 t·m
ACCEPTANCE CHECK
At a 23.0 m radius, capacity ≥ 7.5 t and hook height ≥ 24.0
m.
13.
Recommended selection procedure13
01
Prepare the building and site layout.
06
Select technically feasible crane models.
02
List erection operations and quantities.
07
Check every critical case on the load chart.
03
Group elements by mass, height and position.
08
Confirm movement, tracks and full lifting paths.
04
Identify the heaviest, highest and farthest cases.
09
Compare cost, productivity, labour and duration.
05
Calculate Qreq, Hreq, lreq, Lreq and Mreq.
10
Document the selected configuration and limits.
The sequence prevents an economical but technically unsafe option from reaching the final comparison.
14.
Common mistakes×
Nominal capacity
×
Rigging mass
×
Critical lift
×
Radius origin
Using the crane maximum capacity instead of capacity
at the required radius.
Omitting slings, spreader beams and hook attachments.
Checking only the heaviest element and ignoring the
highest or farthest one.
Measuring radius from the crane edge instead of the
rotation axis.
14
×
Clearances
×
Ground conditions
×
Hourly price
×
Load moment
Ignoring boom-to-building and boom-to-load distances.
Ignoring bearing capacity, excavations and underground
services.
Comparing rental rates without mobilization, labour and
schedule effects.
Treating load moment as a substitute for the
manufacturer load chart.
Every calculation must match the planned crane configuration and actual operating radius.
15.
Conclusion15
Crane selection combines five decisions
Qreq
Hreq
lreq
Lreq
Mreq
CAPACITY
HEIGHT
RADIUS
BOOM
MOMENT
The selected crane must meet every governing parameter simultaneously in the
planned configuration and at the actual working radius.
Among technically safe alternatives, choose the option with the lowest justified total cost and labour
input.
Lecture 9
Crane Selection and Techno-Economic Evaluation