Construction of Reservoir, Sedimentation Tank & Irrigation System at Berry Farms in Uzbekistan. Company "Debyut"

1.

Construction of Reservoir,
Sedimentation Tank & Irrigation
System at Berry Farms in
Uzbekistan
Bi-weekly Report
04th March 2023

2.

Agenda
#
Description
1
Present the progress made during the past week (01st March to 04th of March).
2
Issues and concerns
2

3.

3
Dashboard
Project
Description:
Summary:-
2 sumps are being worked on in parallel and works are being carried
out in accordance with quality and standard rules
About 17 techniques are involved for water reservoirs till today
Earthwork excavations, leveling and compaction works are being
monitored daily
Reservoir: Excavation works commenced on 09.02.2023
Pre-water: Setting out completed.
Irrigation:
Project Performance:- Irrigation
System
Project Performance:Reservoir
700 000,00
649K
600 000,00
2 000 000,00
1 800 000,00
PV
1.749M
PV
1 600 000,00
Название оси
500 000,00
1 400 000,00
1 200 000,00
400 000,00
1 000 000,00
300 000,00
800 000,00
200 000,00
600 000,00
EV
EV
400 000,00
100 000,00
200 000,00
0,00
Название оси
SPI (value) = 1.24 = (EV/PV)
16/5
0,00
16/5
SPI (value) = 1.04
Legend:
Base Line –
Actual -
3

4.

4
Reservoir & Pre-Waterpool
Progress
Overview:
Roads were made for the smooth movement
of machinery
Excavation in the segmentation tank is almost
complete
Photos:-
Reservoir:2023
Development Key Items
Status Update
Agreed
Planned %
Actual
Var
Earthwork Excavation
60%
54%
-6%
Levelling & Compaction
53%
25%
-28%
Installation of Geo-Textile
0%
0%
0%
Installation of Geomembrane
0%
0%
0%
Concrete Platform (1.5m wide)
0%
0%
0%
Installation of Fence
0%
0%
0%
Feb
Mar
Apr
May
UPDATED 28.02.2023
ON 30.06.22
Pre-Waterpool
Development Key
Items
Agreed
Planned %
Actual
Var
Earthwork excavation
80%
100%
20%
Gravel Filling & Compaction
80%
100%
20%
Polyethene Film
Instalaltion - (Min 1000
Guage)
0%
0%
0%
Concrete Base Slab
0%
0%
0%
Installation of Water Bar
(bentotine)
0%
0%
0%
Walls & Concrete Platform
0%
0%
0%
Feb
Mar
Apr
May
4

5.

5
Reservoir & Pre-Waterpool (time to deliver the job)

Name of work (MAIN RESERVOIR)
Time to deliver the job
Actual
1
Earthwork excavation
8 February – 20 March (40 days)
54%
2
Leveling & Compaction
8 February – 25 March (45 days)
25%
3
Installation Geo-Textile
25 March – 5 April (11 days)
0%
4
Installation Geo-Membrane
5 April – 25 April (20 days)
0%
5
Concrete platform (1.5 wide)
25 April – 15 May (20 days)
0%
6
Installation of Fence
15 May – 23 May (8 days)
0%

Name of work (SEDIMENTATION BASIN)
Time to deliver the job
Actual
1
Earthwork excavation
8 February – 10 March (30 days)
100%
2
Gravel Filling & Compaction
8 February – 10 March (30 days)
100%
3
Polythene Film Installation (1000 Min Gauge)
10 March – 15 March (5 days)
0%
4
Concrete Base Slab
31 March – 10 April (10 days)
0%
5
Installation Water Bar
25 March – 20 April (26 days)
0%
6
Walls & Concrete Platform
20 March – 31 March (11 days)
0%

6.

6
Irrigation System
Progress
Overview:
Irrigation System:-
Basically, Now, tranches of strawberry sub
main lines are excavated
almost 2000 trenches were dug
Agreed
Planned
%
Actual
Var
Tranch excavation & Back
46%
66%
20%
Cherry Farm - Head Unit
0%
0%
0%
Cherry Farm - Main Trench Line
-4%
8%
-12%
Cherry Farm - SubMain Trench Line
46%
87%
41%
Irrigation Valves & RTU
0%
0%
0%
Drip Line and accessories
0%
0%
0%
Head Unit
0%
0%
0%
Main Trench Line
45%
89%
44%
SubMain Trench Line
42%
78%
36%
Irrigation Valves & RTU
0%
0%
0%
Drip Line and accessories
0%
0%
0%
Testing & Commissioning
0%
0%
0%
Feb
Mar
Development Key Items
Photos:-
Apr
May
Blueberry , Blackberry, Raspberry & Strawberrry Farm
Handover
6

7.

7
Irrigation System (time to deliver the job)

Description of works
Time to deliver the job
Actual
1
Tranch excavation & back
10 February – 30 March (48 days)
66,32%

Cherry Farm
Time to deliver the job
Actual
1
Cherry Farm –Head Unit
31 March – 10 April (10 days)
0%
2
Cherry Farm –Main Trench Line
5 March – 30 March (25 days)
7,86%
3
Cherry Farm –Submain Trench Line
10 February – 30 March (48 days)
88,15%
4
Irrigation valves & RTU
5 April – 10 May (35 days)
0%
5
Drip Line and accessories
5 April – 25 May (20 days)
0%

Blueberry, Blackberry, Raspberry, strawberry
Time to deliver the job
Actual
1
Head Unit
31 March – 10 April (10 days)
2
Main Trench Line
11 February – 30 March (47 days)
88,61%
3
Submain Trench Line
13 February – 30 March (45 days)
78,35%
4
Irrigation valves & RTU
5 April – 10 May (35 days)
0%
5
Drip Line and accessories
5 April – 27 May (52 days)
0%
6
Testing & Commissioning
25 May – 27 May (2 days)
0%
7
Handover
27 May – 31 May (2 days)
0%

8.

Area of Concerns
ISSUES & CONCERNS
• Due to the fact that it is winter now, there are problems with moving equipment in the field, earthwork excavation of segmentation
and main tanks, compaction them, and digging trenches. Techniques are sinking in the mud.
• A separate working group has been assigned the task of completing the amenities specified on Appendix A.
• Due to the fact that there are residential areas around the facility, the technics cannot work until late at night
All information given in percentages are shown regarding 4 days (from 1st till 4th March)
Main Reservoir
• Earthwork excavation was done 15% for 4 days. Excavation works reached 54%.
• Leveling & Compaction remained unchanged and it stands with 25%.
Sedimentation Basin
• Earthwork excavation was done 10% within 4 days and Excavation works reached 100%.
• Gravel Filling & Compaction was done 10% and reached 100%.
Irrigation system
• Trench excavation & Back was done 24,32% within 4 days and reached 66,32%.
8

9.

Project Schedule (Reservoir)
Legend:
Base Line –
Actual -
9

10.

Project Schedule (Irrigation)
Legend:
Base Line –
Actual -
10

11.

Project Schedule (Irrigation)

12.

Progress Photos
1212

13.

Progress Photos
1313

14.

Debyut
P.O. Box 2297, Abu Dhabi,
United Arab Emirates
[email protected]
+971 2 554 1000
agritek.ae
Thank You