Start a new project
The MS Project interface
Schedule a Project from a Start or Finish Dates
Setting working Days
Working with Tasks List
Task Information
Creating Tasks Relationships
Lag
SF Start-to-Finish Relationship
Showing Critical Path
Project Statistics
Working with Resources List
Assigning Resources to Tasks
Assigning Resources to Tasks
Assigning Resources to Tasks
Over allocated Task Resource
Calculate project
Project Statistics – Cost Updated
Task Usage View
Task Form
Resources Form
Resources Using View
Team Planner View
Calendar View
Resource Overview Report
Cost Overruns Report
Printing the Project Map

MS Project 2016. Getting Started

1.

MS Project 2016
Getting Started

2. Start a new project

There are a lot of
different templates and
themes like Software
development plan and
Agile project
management.

3. The MS Project interface

Toolbar
Ribbon
Main Screen
components

4. Schedule a Project from a Start or Finish Dates

5. Setting working Days

6.

Gantt Chart
Task
Gantt Diagram

7. Working with Tasks List

Adding the essential data of tasks :
1. Task name
2. Duration (D, W, H, M, Mo)
3. Start date
4. End date
5. % Complete

8. Task Information

Editing task. Adding resource.
Changing dates

9. Creating Tasks Relationships

MS project will calculate dates
based on the durations of the
tasks, their relationships and the
start date set for the project,
however it is possible to change
the starting date of a task (if
necessary) By double clicking on
a Task or milestone, and using
the fields related to the dates
(Start or Finish).

10.

FS Finish-to-Start Relationship
Predecessors
FS
Duration
Task/Resources
Successors

11.

SS Start-to-Start Relationship
Predecessors
SS
Task/Resources
Successors

12.

FF Finish-to-Finish Relationship
Predecessors
FF
Task/Resources
Successors

13. Lag

Predecessors
Lag
Task/Resources
Successors

14. SF Start-to-Finish Relationship

Predecessors
SF
Task/Resources
Successors

15.

Overlap
Predecessors
Overlap
Task/Resources
Successors

16.

The Critical Path
CP is the flow of tasks, of which, a delay in any
one of
these tasks will cause a delay to the project.
It is the longest path through the project
network diagram and the shortest possible time
to complete the project.

17. Showing Critical Path

18. Project Statistics

Go to File -> Info -> Project Information

19. Working with Resources List

You can use the Resource Sheet to create a list of the people,
equipment, and material resources.

20. Assigning Resources to Tasks

Assign Resources Using Task List Resources Name Column

21. Assigning Resources to Tasks

Assign Resources Using Task Information, Resources Tab

22. Assigning Resources to Tasks

Assign Resources Using Resource Tab

23. Over allocated Task Resource

MS Project helps you by giving some “Red man” icons and
yellow exclamation mark when your resource is owerlocated
or you have some problems with amounts of money

24. Calculate project

25. Project Statistics – Cost Updated

26. Task Usage View

27. Task Form

28. Resources Form

29. Resources Using View

30. Team Planner View

31. Calendar View

32. Resource Overview Report

33. Cost Overruns Report

34. Printing the Project Map

35.

Thank You
English     Русский Правила